PROJECT NAME : Vedic Kendra |
Project Detail/Brief Description: |
Project Department: Shri Kashi Vishwanath Dham |
Associated Yojna Name: Shri Kashi Vishwanath Dham |
||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER/INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
SK Prajapati | sk.prajapati@pspprojects.com | 7069073757 | Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 28/Apr/2020 | Project Planned Completion Date: 02/Aug/2021 |
METRICS | ||
---|---|---|
Key Metrics | Current | Planned |
Number of people using community toilet | 2100-2200 Users | 1800-2500 Users |
SCHEDULE | |||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | |||||||||||||||||||||||||
1 | Sub Structure Works
| 28/04/2020 | 05/12/2020 | - | 0% | ||||||||||||||||||||||||||
2 | Super Structure Works
| 07/10/2020 | 04/04/2021 | - | 0% | ||||||||||||||||||||||||||
3 | Finishing Works | 06/12/2020 | 02/08/2021 | - | 0% |