PROJECT NAME : Yatri Suvidha Kendra II |
Project Detail/Brief Description: |
Project Department: Shri Kashi Vishwanath Dham |
Associated Yojna Name: Shri Kashi Vishwanath Dham |
||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER/INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
SK Prajapati | sk.prajapati@pspprojects.com | 7069073757 | Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 20/Mar/2020 | Project Planned Completion Date: 13/Apr/2021 |
METRICS | ||
---|---|---|
Key Metrics | Current | Planned |
HT & LT cabling and line | 0 KM | 167 KM |
Increase power capacity | 0 | 20 MVA |
Replacement of LT overhead line by Aerial Bunch Cable | 0 | 362 |
SCHEDULE | ||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | ||||||||||||||||||||||||||||||
1 | Sub Structure Works
| 20/03/2020 | 16/08/2021 | - | 0% | |||||||||||||||||||||||||||||||
2 | Super Structure Works
| 18/06/2020 | 03/01/2021 | - | 0% | |||||||||||||||||||||||||||||||
3 | Finishing Works | 17/08/2020 | 13/04/2021 | - | 0% |