PROJECT NAME : Utility Block |
Project Detail/Brief Description: |
Project Department: Shri Kashi Vishwanath Dham |
Associated Yojna Name: Shri Kashi Vishawanath Dham |
||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER/INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
SK Prajapati | sk.prajapati@pspprojects.com | 7069073757 | Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 18/Apr/2020 | Project Planned Completion Date: 15/Jul/2021 |
METRICS | ||
---|---|---|
Key Metrics | Current | Planned |
Length of flyover 1710m | The progress up to 31-10-2017 is 28.93% | 31-12-2018 |
SCHEDULE | |||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | |||||||||||||||||||||||||
1 | Sub Structure Works
| 18/04/2020 | 26/01/2021 | - | 0% | ||||||||||||||||||||||||||
2 | Super Structure Works
| 29/10/2020 | 26/04/2021 | - | 0% | ||||||||||||||||||||||||||
3 | Finishing Works | 13/12/2020 | 15/07/2021 | - | 0% |