PROJECT NAME : Toilet Block |
Project Detail/Brief Description: |
Project Department: Shri Kashi Vishwanath Dham |
Associated Yojna Name: Shri Kashi Vishwanath Dham |
||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER/INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
SK Prajapati | sk.prajapati@pspprojects.com | 7069073757 | Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 07/Apr/2020 | Project Planned Completion Date: 16/Mar/2021 |
METRICS | ||
---|---|---|
Key Metrics | Current | Planned |
Capacity of Sewage Treatment | 80 (MLD) | 220 (MLD) |
Biological Oxygen Demand | 150-200 mg/L | 30 mg/L |
Chemical Oxygen Demand | 300-350 mg/L | 50 mg/L |
SCHEDULE | |||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | |||||||||||||||||||||||||
1 | Sub Structure Works
| 07/04/2020 | 17/10/2020 | - | 0% | ||||||||||||||||||||||||||
2 | Super Structure Works
| 19/08/2020 | 16/12/2020 | - | 0% | ||||||||||||||||||||||||||
3 | Finishing Works | 03/10/2020 | 16/03/2021 | - | 0% |