Back

Project Details

PROJECT NAME :  Shop III
Project Detail/Brief Description:


Project Department:

Shri Kashi Vishwanath Dham

Associated Yojna Name:

Shri Kashi Vishawanath Dham

Goals, Objectives and Benefits of Project:


PROJECT MANAGER/INCHARGE
 Name Email Contact Designation
SK Prajapati sk.prajapati@pspprojects.com 7069073757 Project Manager

 PROJECT DATES
Project Planned Start Date: 30/Mar/2020 Project Planned Completion Date: 14/May/2021

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Sub Structure Works
TaskDescriptionStart Date End DateStatus
Piling work & Excavation work underway Piling work & Excavation work underway 30/11/-0001 30/11/-0001 0%
Restoration work Restoration work 30/11/-0001 30/11/-0001 0%
30/03/2020 07/10/2020 - 0%
2 Super Structure Works
TaskDescriptionStart Date End DateStatus
Ground floor roof work Ground floor roof work 30/11/-0001 30/11/-0001 0%
First-floor roof work First-floor roof work 30/11/-0001 30/11/-0001 0%
Second-floor roof Second-floor roof 30/11/-0001 30/11/-0001 0%
Terus work Terus work 30/11/-0001 30/11/-0001 0%
14/07/2020 29/01/2021 - 0%
3 Finishing Works
28/08/2020 14/05/2021 - 0%