PROJECT NAME : Shop I |
Project Detail/Brief Description: |
Project Department: Shri Kashi Vishwanath Dham |
Associated Yojna Name: Shri Kashi Vishwanath Dham |
||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER/INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
SK Prajapati | sk.prajapati@pspprojects.com | 7069073757 | Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 15/Mar/2020 | Project Planned Completion Date: 14/Mar/2021 |
SCHEDULE | |||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | |||||||||||||||||||||||||
1 | Sub Structure Works
| 15/03/2020 | 11/08/2020 | - | 0% | ||||||||||||||||||||||||||
2 | Super Structure Works
| 13/06/2020 | 09/11/2020 | - | 0% | ||||||||||||||||||||||||||
3 | Finishing Works | 12/08/2020 | 14/03/2021 | - | 0% |