PROJECT NAME : Shop II |
Project Detail/Brief Description: |
Project Department: Shri Kashi Vishwanath Dham |
Associated Yojna Name: Shri Kashi Vishwanath Dham |
||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER/INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
SK Prajapati | sk.prajapati@pspprojects.com | 7069073757 | Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 20/Mar/2020 | Project Planned Completion Date: 14/Apr/2021 |
METRICS | ||
---|---|---|
Key Metrics | Current | Planned |
Erection & commissioning of 34Nos 11KV Feeders | 4 Nos Feeder completed & 19 nos. Feeder erection work are under progress | 3Nos Feeder( Kotwa-1st, Viraon and Babatpur) will be completed in Nov,17, 4Nos (Rupapur, Miraja Murad, Kalikadham n and Badagaon)in Dec,17 & 3Nos (Sakalpur, Nehwanipur and Aura)in Jan,18 |
SCHEDULE | |||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | |||||||||||||||||||||||||
1 | Sub Structure Works
| 20/03/2020 | 27/08/2020 | - | 0% | ||||||||||||||||||||||||||
2 | Super Structure Works
| 14/07/2020 | 10/12/2020 | - | 0% | ||||||||||||||||||||||||||
3 | Finishing Works | 12/09/2020 | 14/04/2021 | - | 0% |