PROJECT NAME : Multi Purpose Hall |
Project Detail/Brief Description: |
Project Department: Shri Kashi Vishwanath Dham |
Associated Yojna Name: Shri Kashi Vishwanath DHam |
||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER/INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
SK Prajapati | sk.prajapati@pspprojects.com | 7069073757 | Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 15/Apr/2020 | Project Planned Completion Date: 29/Apr/2021 |
METRICS | ||
---|---|---|
Key Metrics | Current | Planned |
Number of House holds connected through Main Sewage line in Trans Varuna Area | 0 | 50,000 |
SCHEDULE | |||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | |||||||||||||||
1 | Sub Structure Works
| 15/04/2020 | 31/10/2020 | - | 0% | ||||||||||||||||
2 | Super Structure Works | 14/07/2020 | 10/03/2021 | - | 0% | ||||||||||||||||
3 | Finishing Works | 12/09/2020 | 29/04/2021 | - | 0% |