PROJECT NAME : Jetty And Ghat Finishing |
Project Detail/Brief Description: |
Project Department: Shri Kashi Vishwanath Dham |
Associated Yojna Name: Shri Kashi Vishwanth Dham |
||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER/INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
SK Prajapati | sk.prajapati@pspprojects.com | 7069073757 | Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 25/Feb/2020 | Project Planned Completion Date: 30/Mar/2021 |
METRICS | ||
---|---|---|
Key Metrics | Current | Planned |
Total land under Acquisition 211.77 ha. Length = 59.02 km | 54.56% of land only is physically available as on date | Entire land acquisition is planned to be completed by 31st December 2017 |
SCHEDULE | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | ||||||||||
1 | Dredging for Diaphragm Wall | 10/04/2020 | 10/05/2020 | - | 0% | |||||||||||
2 | Diaphragm Wall | 01/04/2020 | 31/07/2020 | - | 0% | |||||||||||
3 | Dredging for Jetty | 01/05/2020 | 09/06/2020 | - | 0% | |||||||||||
4 | Jetty I
| 01/06/2020 | 31/07/2020 | - | 0% | |||||||||||
5 | Jetty II | 01/12/2020 | 30/03/2021 | - | 0% |