PROJECT NAME : Guest House (Tourist) |
Project Detail/Brief Description: |
Project Department: Shri Kashi Vishwanath Dham |
Associated Yojna Name: Shri Kashi Vishwnath Dham |
||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER/INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
SK Prajapati | sk.prajapati@pspprojects.com | 7069073757 | Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 05/Apr/2020 | Project Planned Completion Date: 19/Apr/2021 |
METRICS | ||
---|---|---|
Key Metrics | Current | Planned |
No. of House holds benefiting by this project | 1.09 Lacs | 1.59 Lacs |
No. of New Connections | 0 No. | 50028 No. |
SCHEDULE | |||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | |||||||||||||||||||||||||
1 | Sub Structure Works
| 05/04/2020 | 22/08/2021 | - | 0% | ||||||||||||||||||||||||||
2 | Super Structure Works
| 29/06/2020 | 05/03/2021 | - | 0% | ||||||||||||||||||||||||||
3 | Finishing Works | 13/08/2020 | 19/04/2021 | - | 0% |