PROJECT NAME : Godowlia Gate |
Project Detail/Brief Description: |
Project Department: Shri Kashi Vishwanath Dham |
Associated Yojna Name: Shri Kashi Vishwanath Dham |
||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER/INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
SK Prajapati | sk.prajapati@pspprojects.com | 7069073757 | Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 21/Apr/2020 | Project Planned Completion Date: 10/Aug/2021 |
METRICS | ||
---|---|---|
Key Metrics | Current | Planned |
Construction of ROB at Railway Crossing no 4 C | NIL | Constrution of ROB at Crossing No.-4C |
Construction of ROB at Railway Crossing No 5 C | NIL | Constrution of ROB at Crossing No.-5C |
Construction of Bridge over river Varuna at Imiliya ghat | NIL | Construction of Morag Bridge on river Varuna |
Construction of 04 lane road from Lahartara to Shivpur | Single lane road in length 1.0 Km | Construction of 04 lane road in length 5.33 km |
SCHEDULE | |||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | |||||||||||||||||||||||||
1 | Sub Structure Works
| 21/04/2020 | 13/02/2021 | - | 0% | ||||||||||||||||||||||||||
2 | Super Structure Works
| 05/01/2021 | 03/06/2021 | - | 0% | ||||||||||||||||||||||||||
3 | Finishing Works | 19/02/2021 | 10/08/2021 | - | 0% |