PROJECT NAME : Mandir Chowk |
Project Detail/Brief Description: |
Project Department: Shri Kashi Vishwanath Dham |
Associated Yojna Name: Shri Kashi Vishwanath Dham |
||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER/INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
SK Prajapati | sk.prajapati@pspprojects.com | 7069073757 | Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 16/Feb/2020 | Project Planned Completion Date: 29/Jun/2021 |
SCHEDULE | |||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) | |||||||||||||||||||||||||
1 | Sub Structure Works
| Sub Structure Works | 16/02/2020 | 02/09/2020 | - | 15% | |||||||||||||||||||||||||
2 | Super Structure Works
| Super Structure Works | 16/05/2020 | 30/04/2021 | - | 10% | |||||||||||||||||||||||||
3 | Finishing Works | Finishing Works | 15/07/2020 | 29/06/2021 | - | 10% | |||||||||||||||||||||||||
4 | sub structural work | sub structural work | 02/02/2020 | 30/05/2020 | - | 50% |